Difference between revisions of "Beacon4"
From Hackstrich
(Status updates.) |
|||
(11 intermediate revisions by the same user not shown) | |||
Line 2: | Line 2: | ||
= Project Status = | = Project Status = | ||
+ | * 2013-09: Project assembled (with LED strips hung from a frame) at Mini Maker Faire 2013 as a backdrop for the HackLab.TO table. Mostly worked, but had one IO-ETH module fail, need to respin this without any QFNs on it to resolve reliability issues. Used ArtnetForProcessing instead of LightJams, and had no software issues this time. | ||
+ | * 2012-11-24: Wrote up lessons learned and the log of what happened on-playa. Will still continue to look into the tech issues we had scalability-wise, but other than that Beacon4 is considered to be complete. The [[StrichLux]] hardware that was used will be reused next year for [[InvisibleMaze]]. | ||
+ | * BRC2012: Project went up (partly) at Burning Man 2012, many lessons were learned, and it looked cool. See Lessons Learned section for more details. | ||
+ | * 2012-08-21: Fixed StrichLux C board set (bad soldering on a level shifter on an IO-SPI shorting out a power rail), found the slow refresh rate bug was actually VMware Fusion dropping UDP packets on my laptop, won't be an issue on the real thing as there's no VMware. | ||
+ | * 2012-08-20: Shipped all cabling, all LED strips (except the 1m test strip S33), StrichLux A and B, and the PC box w/ PC. StrichLux enclosure C shipped but the board set is still here to try to get it fixed/working properly, and to try to fix the slow refresh rate bug. Woot! | ||
+ | * 2012-08-19: Another 12h workday. All cabling terminated, all boards populated, all PWR-DC5s working well enough to use. StrichLux C's CORE board seems to not work, as the system sends no data out. Partial system was set up with StrichLux A and B and sort of worked, excep the refresh issue on higher channel numbers is still there and makes 3/4 almost useless. Supposed to ship tomorrow, but I don't see how it can. | ||
+ | * 2012-08-18: Epic workday. All PWR-DC5s done (but one channel on one not working yet), connectors added to the 2 COREs that didn't have them and all IO-SPIs that didn't have them, all feeders, jumpers, and strips labeled, all feeders except two connectorized, power feeders purchased and connectorized. | ||
+ | * 2012-08-17: Signal wiring terminated, but not yet inserted into the Mini-Fit plastic shells. | ||
+ | * 2012-08-15: Foam cut to fit, Sabres terminated. | ||
+ | * 2012-08-14: All in-box high power connectors are terminated except Sabre-side of the inputs. Tomorrow will get signal wiring terminated and all wiring installed in boxes. | ||
+ | * 2012-08-13: All connectors mounted on the 3 StrichLux boxes. Wiring of B and C still needs to be done. | ||
* 2012-08-12: All LED strip now cut/terminated/sealed. Test of StrichLux A channels 1-3 are working mostly, though each higher numbered channel seems to refresh slower than the one before it. More troubleshooting will need to be done. | * 2012-08-12: All LED strip now cut/terminated/sealed. Test of StrichLux A channels 1-3 are working mostly, though each higher numbered channel seems to refresh slower than the one before it. More troubleshooting will need to be done. | ||
* 2012-08-11: StrichLux A enclosure has all connectors mounted and wired up (except only 1/2 of the power connector so far). | * 2012-08-11: StrichLux A enclosure has all connectors mounted and wired up (except only 1/2 of the power connector so far). | ||
Line 27: | Line 38: | ||
*2012-04-23: Requested permission from NeonBunny to attach LEDs to the tower. | *2012-04-23: Requested permission from NeonBunny to attach LEDs to the tower. | ||
*2012-04-22: Started putting together idea. | *2012-04-22: Started putting together idea. | ||
+ | |||
+ | = On-Playa = | ||
+ | == Overview == | ||
+ | * Project took many days of work to set up, and only ever got about 2/3 of it put up | ||
+ | ** Setup took a lot more time away from enjoying BRC than I would have liked, need to emphasize quick setup time more next time | ||
+ | * Channels 3/4 on each control box were essentially useless due to the lighting control software not scaling | ||
+ | ** Resulted in only having 6 total channels available (2 from each of the 3 boxes) | ||
+ | * Same MAC address was accidently programmed into each [[StrichLux/IO-ETH|IO-ETH]], meaning that whatever was sent to channel X on one box went to channel X on all boxes (Art-Net is UDP broadcast) | ||
+ | ** Resulted in having only two channels of unique data total, each duplicated 3 times | ||
+ | ** Had everything we needed to reprogram the boards (as an issue like this was thought to be likely) but the diagnostic PC wouldn't talk to the PICkit3 | ||
+ | * Only one cabling issue, data/clock were backwards on one cable | ||
+ | ** Given the other issues, this segment was abandoned and others were connected instead | ||
+ | * The parts that went up still looked cool, and got a lot of positive comments | ||
+ | |||
+ | == Lessons Learned == | ||
+ | * Way too much running around/stress/work at the last minute before it shipped | ||
+ | ** '''Lesson: Start earlier, set milestones and scale the project back/put it off until the next year if they aren't met''' | ||
+ | * Shipping was a nightmare | ||
+ | ** Took longer than expected/guaranteed due to customs, project almost didn't get there before we departed for BRC | ||
+ | ** Cost over $1000 all together as tax/duty had to be paid both ways | ||
+ | ** '''Lesson: Ship much earlier (ideally beginning of August) and consider shipping with another large local project or the Big Ole' Truck''' | ||
+ | ** '''Lesson: Ship as Strich Labs under the program designed for shipping things down for demos that will then return''' | ||
+ | * Lack of good documentation meant that the setup work couldn't be efficiently parallelized | ||
+ | ** '''Lesson: Put more of a priority on documentation that others can read/understand to help set the project up''' | ||
+ | * Amount of cabling required to be sorted out/pulled/secured made the project take a huge amount of time to set up | ||
+ | ** Documentation would have helped parallelize setup if it was available, which would have made it a bit less painful | ||
+ | ** '''Lesson: Minimize cabling wherever possible by having one part attach directly to the previous part''' | ||
+ | ** '''Lesson: Minimize the number of connections between parts where possible''' | ||
+ | * Setup diagram lead to having cables running down one vertical riser, then plugging into a box that wasn't there. | ||
+ | ** This was noted earlier on, but never recorded and was forgotten about. | ||
+ | ** '''Lesson: Document all issues found/thought about on a wiki page immediately, so they're not missed later''' | ||
+ | * Some of the setup was near-impossible due to needing to put LED strips up where there was nothing to stand on | ||
+ | ** Resulted in a lot of overly-dangerous leaning/hanging with one hand while trying to velcro up strips with the other | ||
+ | ** '''Lesson: Think about how the project will be put up, not just the final state it will be in''' | ||
+ | * Same MAC address was programmed into each board | ||
+ | ** Tried to fix it on-playa, but the troubleshooting/programming laptop wouldn't talk to the PICkit3 that was with us | ||
+ | ** '''Lesson: Leave more time to test hardware before it ships''' | ||
+ | ** '''Lesson: Test all troubleshooting/programming equipment that is needed before leaving for BRC''' | ||
+ | * Lighting control software didn't scale properly, only ran two universes well per box | ||
+ | ** '''Lesson: Again, leave more time to test everything well''' | ||
+ | ** '''Lesson: Minimize software that isn't under directly under our control''' | ||
+ | * Fit-PC 2i worked as-expected other than producing more heat than we had figured | ||
+ | ** Needed to leave the Pelican case with the control PC in it slightly open during operation | ||
+ | ** '''Lesson: Need to do better thermal calculations/testing on any high-power equipment in the future''' | ||
+ | * Toughbook CF-U1 UMPC worked great, no issues with it other than needing one recharge during burn | ||
+ | ** Survived rain and being covered in playa with no issues at all | ||
+ | ** Wouldn't have needed recharging at all if things went better | ||
+ | ** Fluke 28 also lived up to expectations, no issues at all despite getting wet and covered in playa | ||
+ | ** '''Lesson: Reliable troubleshooting equipment is really important! This was totally worth the research/money put into it.''' | ||
= Outstanding Issues = | = Outstanding Issues = | ||
Line 631: | Line 691: | ||
== Feeders and Jumpers == | == Feeders and Jumpers == | ||
* Feeders | * Feeders | ||
− | ** Feeder A-1 - 310cm | + | ** Feeder A-1 - 310cm (F01) |
− | ** Feeder A-2 - 310cm | + | ** Feeder A-2 - 310cm (F02) |
− | ** Feeder A-3 - 310cm | + | ** Feeder A-3 - 310cm (F03) |
− | ** Feeder A-4 - 310cm | + | ** Feeder A-4 - 310cm (F04) |
− | ** Feeder B-1 - 360cm | + | ** Feeder B-1 - 360cm (F05) |
− | ** Feeder B-2 - 360cm | + | ** Feeder B-2 - 360cm (F06) |
− | ** Feeder B-3 - 360cm | + | ** Feeder B-3 - 360cm (F07) |
− | ** Feeder B-4 - 711cm | + | ** Feeder B-4 - 711cm (F08) |
− | ** Feeder C-1 - 576cm | + | ** Feeder C-1 - 576cm (F09) |
− | ** Feeder C-2 - 576cm | + | ** Feeder C-2 - 576cm (F10) |
− | ** Feeder C-3 - 516cm | + | ** Feeder C-3 - 516cm (F11) |
− | ** Feeder C-4 - 687cm | + | ** Feeder C-4 - 687cm (F12) |
* Jumpers | * Jumpers | ||
− | ** Jumper A-1 - 308cm | + | ** Jumper A-1 - 308cm (J01) |
− | ** Jumper A-2 - 262cm | + | ** Jumper A-2 - 262cm (J02) |
− | ** Jumper A-3 - 308cm | + | ** Jumper A-3 - 308cm (J03) |
− | ** Jumper A-4 - 262cm | + | ** Jumper A-4 - 262cm (J04) |
− | ** Jumper B-3 - 92cm | + | ** Jumper B-3 - 92cm (J05) |
− | ** Jumper B-4 - 152cm | + | ** Jumper B-4 - 152cm (J06) |
− | ** Jumper C-1.1 - 73cm | + | ** Jumper C-1.1 - 73cm (J07) |
− | ** Jumper C-1.2 - 142cm | + | ** Jumper C-1.2 - 142cm (J08) |
− | ** Jumper C-2.1 - 73cm | + | ** Jumper C-2.1 - 73cm (J09) |
− | ** Jumper C-2.2 - 142cm | + | ** Jumper C-2.2 - 142cm (J10) |
− | ** Jumper C-3 - 92cm | + | ** Jumper C-3 - 92cm (J11) |
− | + | ||
− | + | === Pinouts === | |
− | + | ==== Power+Data Cables ==== | |
− | + | {| class="wikitable sortable" border="1" | |
− | + | |- | |
+ | ! Signal | ||
+ | ! Wiring Colour | ||
+ | ! MX150L Pin | ||
+ | ! RT360 Pin | ||
+ | |- | ||
+ | | GND | ||
+ | | White | ||
+ | | 1 | ||
+ | | A | ||
+ | |- | ||
+ | | +5V | ||
+ | | Black | ||
+ | | 2 | ||
+ | | B | ||
+ | |- | ||
+ | | Data | ||
+ | | Red | ||
+ | | 3 | ||
+ | | 1 | ||
+ | |- | ||
+ | | Clock | ||
+ | | Green | ||
+ | | 4 | ||
+ | | 2 | ||
+ | |} | ||
+ | |||
+ | ==== Power Only Cables ==== | ||
+ | {| class="wikitable sortable" border="1" | ||
+ | |- | ||
+ | ! Signal | ||
+ | ! Wiring Colour | ||
+ | ! RT360 Pin | ||
+ | |- | ||
+ | | Bus A+B Negative | ||
+ | | Black | ||
+ | | A | ||
+ | |- | ||
+ | | Bus A Positive | ||
+ | | Green | ||
+ | | B | ||
+ | |- | ||
+ | | N/C | ||
+ | | N/C | ||
+ | | C | ||
+ | |- | ||
+ | | Bus B Positive | ||
+ | | White | ||
+ | | D | ||
+ | |} | ||
= StrichLux Enclosures = | = StrichLux Enclosures = | ||
Line 889: | Line 998: | ||
|- | |- | ||
| 12 sets of StrichLux IO-SPI Parts | | 12 sets of StrichLux IO-SPI Parts | ||
− | | | + | | Obtained |
− | | align=right | | + | | align=right | $190.39 |
|- | |- | ||
| Enclosure A | | Enclosure A | ||
Line 927: | Line 1,036: | ||
| Obtained | | Obtained | ||
| align=right | $113.00 | | align=right | $113.00 | ||
+ | |- | ||
+ | | Shipping (outbound) | ||
+ | | Done | ||
+ | | align=right | $455.92 | ||
+ | |- | ||
+ | | Tax/Duty (outbound) | ||
+ | | Done | ||
+ | | align=right | $104.40 | ||
+ | |- | ||
+ | | Shipping (return) | ||
+ | | Done | ||
+ | | align=right | $224.29 | ||
+ | |- | ||
+ | | Tax/Duty (return) | ||
+ | | Done | ||
+ | | align=right | $443.06 | ||
|- | |- | ||
| '''Total''' | | '''Total''' | ||
| '''Ordered''' | | '''Ordered''' | ||
− | | align=right | $ | + | | align=right | $6668.90 |
|- | |- | ||
| '''Total''' | | '''Total''' | ||
| '''Future''' | | '''Future''' | ||
− | | align=right | | + | | align=right | $0.00 |
|- | |- | ||
| '''Grand Total''' | | '''Grand Total''' | ||
| | | | ||
− | | align=right | | + | | align=right | $6668.90 |
+ | |- | ||
+ | | '''Hours Spent''' | ||
+ | | | ||
+ | | align=right | 577 | ||
|} | |} | ||
Line 946: | Line 1,075: | ||
</gallery> | </gallery> | ||
− | [[Category: | + | [[Category:Completed Projects]] |
Latest revision as of 00:23, 27 September 2013
Beacon4 will be the fourth incarnation of the flagpole beacon (after Beacon2 and Beacon3), for Burning Man 2012. This year the plan is to take a different approach, and light the entire scaffold tower rather than just a beacon on top of the flagpole.
Contents
Project Status
- 2013-09: Project assembled (with LED strips hung from a frame) at Mini Maker Faire 2013 as a backdrop for the HackLab.TO table. Mostly worked, but had one IO-ETH module fail, need to respin this without any QFNs on it to resolve reliability issues. Used ArtnetForProcessing instead of LightJams, and had no software issues this time.
- 2012-11-24: Wrote up lessons learned and the log of what happened on-playa. Will still continue to look into the tech issues we had scalability-wise, but other than that Beacon4 is considered to be complete. The StrichLux hardware that was used will be reused next year for InvisibleMaze.
- BRC2012: Project went up (partly) at Burning Man 2012, many lessons were learned, and it looked cool. See Lessons Learned section for more details.
- 2012-08-21: Fixed StrichLux C board set (bad soldering on a level shifter on an IO-SPI shorting out a power rail), found the slow refresh rate bug was actually VMware Fusion dropping UDP packets on my laptop, won't be an issue on the real thing as there's no VMware.
- 2012-08-20: Shipped all cabling, all LED strips (except the 1m test strip S33), StrichLux A and B, and the PC box w/ PC. StrichLux enclosure C shipped but the board set is still here to try to get it fixed/working properly, and to try to fix the slow refresh rate bug. Woot!
- 2012-08-19: Another 12h workday. All cabling terminated, all boards populated, all PWR-DC5s working well enough to use. StrichLux C's CORE board seems to not work, as the system sends no data out. Partial system was set up with StrichLux A and B and sort of worked, excep the refresh issue on higher channel numbers is still there and makes 3/4 almost useless. Supposed to ship tomorrow, but I don't see how it can.
- 2012-08-18: Epic workday. All PWR-DC5s done (but one channel on one not working yet), connectors added to the 2 COREs that didn't have them and all IO-SPIs that didn't have them, all feeders, jumpers, and strips labeled, all feeders except two connectorized, power feeders purchased and connectorized.
- 2012-08-17: Signal wiring terminated, but not yet inserted into the Mini-Fit plastic shells.
- 2012-08-15: Foam cut to fit, Sabres terminated.
- 2012-08-14: All in-box high power connectors are terminated except Sabre-side of the inputs. Tomorrow will get signal wiring terminated and all wiring installed in boxes.
- 2012-08-13: All connectors mounted on the 3 StrichLux boxes. Wiring of B and C still needs to be done.
- 2012-08-12: All LED strip now cut/terminated/sealed. Test of StrichLux A channels 1-3 are working mostly, though each higher numbered channel seems to refresh slower than the one before it. More troubleshooting will need to be done.
- 2012-08-11: StrichLux A enclosure has all connectors mounted and wired up (except only 1/2 of the power connector so far).
- 2012-08-06: 35m of LED strip cut/terminated/sealed.
- 2012-08-05: Reels A-I marked for cutting, so far all measurements add up correctly. Plan for tomorrow is to pick up StrichLux C enclosure, customize it, and get all LED strips terminated.
- 2012-08-04: All LED strip wire cut, terminated, and inserted into connectors. StrichLux B enclosure has all connectors drilled. Thermal tests failed running the PC inside a box, will need to add an external radiator.
- 2012-07-29: All feeders and jumpers now have female MX150Ls, and StrichLux A enclosure has output connectors drilled. Plan for tomorrow is to get the LED strip wire (832 inches total, ideally 208 inches/18 feet each of 4 colours) and get it cut into 4 inch pieces.
- 2012-07-28: 9 feeders connectorized with MX150Ls, power and Ethernet jacks installed in StrichLux A enclosure.
- 2012-07-25: All feeders and jumpers cut to length.
- 2012-07-24: Finalized all strip IDs and created an empty project in LightJams that has all fixtures added in their correct places. Built the other two required Core Boards and they power/program OK.
- 2012-07-23: Work on the installation helping system (BITS) is coming along, currently can scan a part and get a 3D model of where it goes. Inter-strip connectors, bulkhead M12 connectors, and Ethernet switch arrived. Cable ordered.
- 2012-07-19: fitPC is here!
- 2012-07-15: Ordered inter-strip connectors and remaining PWR-DC5, CORE, and IO-ETH parts.
- 2012-07-14: First successful end-to-end test of the whole StrichLux system driving 5m of LED strip from the PWR-DC5.
- 2012-07-11: Ordered the switch.
- 2012-07-09: Ordered the majority of enclosure connectors.
- 2012-07-07: First functioning test of StrichLux system driving 5m of LED strip.
- 2012-06-24: LED strips all obtained. Lighting design continues, as does firmware development.
- 2012-06-17: Hardware bring-up and firmware writing continuing. Lightjams is almost certainly going to be the software of choice. Lighting design is coming along.
- 2012-06-07: Work on StrichLux continues. Evaluated lots of software, Lightjams is looking the best at this point, though would require Windows.
- 2012-05-27: Completed rev. 1 StrichLux system design of all modules required for this project and sent all boards off for manufacturing.
- 2012-04-30: Started planning the power architecture for the project.
- 2012-04-29: Work continuing on IO-DMX module.
- 2012-04-24: Permission received!
- 2012-04-23: Requested permission from NeonBunny to attach LEDs to the tower.
- 2012-04-22: Started putting together idea.
On-Playa
Overview
- Project took many days of work to set up, and only ever got about 2/3 of it put up
- Setup took a lot more time away from enjoying BRC than I would have liked, need to emphasize quick setup time more next time
- Channels 3/4 on each control box were essentially useless due to the lighting control software not scaling
- Resulted in only having 6 total channels available (2 from each of the 3 boxes)
- Same MAC address was accidently programmed into each IO-ETH, meaning that whatever was sent to channel X on one box went to channel X on all boxes (Art-Net is UDP broadcast)
- Resulted in having only two channels of unique data total, each duplicated 3 times
- Had everything we needed to reprogram the boards (as an issue like this was thought to be likely) but the diagnostic PC wouldn't talk to the PICkit3
- Only one cabling issue, data/clock were backwards on one cable
- Given the other issues, this segment was abandoned and others were connected instead
- The parts that went up still looked cool, and got a lot of positive comments
Lessons Learned
- Way too much running around/stress/work at the last minute before it shipped
- Lesson: Start earlier, set milestones and scale the project back/put it off until the next year if they aren't met
- Shipping was a nightmare
- Took longer than expected/guaranteed due to customs, project almost didn't get there before we departed for BRC
- Cost over $1000 all together as tax/duty had to be paid both ways
- Lesson: Ship much earlier (ideally beginning of August) and consider shipping with another large local project or the Big Ole' Truck
- Lesson: Ship as Strich Labs under the program designed for shipping things down for demos that will then return
- Lack of good documentation meant that the setup work couldn't be efficiently parallelized
- Lesson: Put more of a priority on documentation that others can read/understand to help set the project up
- Amount of cabling required to be sorted out/pulled/secured made the project take a huge amount of time to set up
- Documentation would have helped parallelize setup if it was available, which would have made it a bit less painful
- Lesson: Minimize cabling wherever possible by having one part attach directly to the previous part
- Lesson: Minimize the number of connections between parts where possible
- Setup diagram lead to having cables running down one vertical riser, then plugging into a box that wasn't there.
- This was noted earlier on, but never recorded and was forgotten about.
- Lesson: Document all issues found/thought about on a wiki page immediately, so they're not missed later
- Some of the setup was near-impossible due to needing to put LED strips up where there was nothing to stand on
- Resulted in a lot of overly-dangerous leaning/hanging with one hand while trying to velcro up strips with the other
- Lesson: Think about how the project will be put up, not just the final state it will be in
- Same MAC address was programmed into each board
- Tried to fix it on-playa, but the troubleshooting/programming laptop wouldn't talk to the PICkit3 that was with us
- Lesson: Leave more time to test hardware before it ships
- Lesson: Test all troubleshooting/programming equipment that is needed before leaving for BRC
- Lighting control software didn't scale properly, only ran two universes well per box
- Lesson: Again, leave more time to test everything well
- Lesson: Minimize software that isn't under directly under our control
- Fit-PC 2i worked as-expected other than producing more heat than we had figured
- Needed to leave the Pelican case with the control PC in it slightly open during operation
- Lesson: Need to do better thermal calculations/testing on any high-power equipment in the future
- Toughbook CF-U1 UMPC worked great, no issues with it other than needing one recharge during burn
- Survived rain and being covered in playa with no issues at all
- Wouldn't have needed recharging at all if things went better
- Fluke 28 also lived up to expectations, no issues at all despite getting wet and covered in playa
- Lesson: Reliable troubleshooting equipment is really important! This was totally worth the research/money put into it.
Outstanding Issues
- How do we attach strips to toe boards?
- Can't ziptie/cable tie like we do everywhere else as the toe boards are wide
Ideas/Plans
- Main idea is to cover most of the scaffold tower in addressable LED strips, driven by multiple StrichLux modules
- Art-Net will be used between the controller and the StrichLux box
- Fit-PC 2i is being looked at to control the whole thing
- As nice as ARM would be power-wise, x86 will be much more flexible software-wise
- Need to make sure it will be powerful enough before we order
- Need to find a fanless very low power 4 or 5 port Ethernet switch
- Allied Telesis AT-FS705LE V5 might work, it's rugged, low power (1.5-2.5W), and cheap
- But it takes 7.5V which would be another regulator and is a potential point of failure that would bring the entire system down
- Alternative option is the GarrettCom S14H-Hi, it takes 8-15V in via screw terminals and is ruggedized, but $140 and draws 4W
- Best option may be the Sixnet SL-5ES-1, it's $100, rugged, takes 10-30VDC via screw terminals, and only draws 2W
- Ended up going with an M12 ethernet switch, the Octopus 5TX EEC
- Allied Telesis AT-FS705LE V5 might work, it's rugged, low power (1.5-2.5W), and cheap
System Components
- Fit-PC 2i (controller)
- Octopus 5TX EEC 5-port Ethernet switch
- 3 StrichLux boxes (driver), each with:
- 60m of LED strips
- Power setup
- Debugging terminal (XO-1? Toughbook?)
Power Details
- Power requirements (peak)
- Fit-PC 2i - ???
- Ethernet Switch - ???
- StrichLux box(es) - ???
- LEDs - 10W/m (~1.8A/m at 5V measured, so 10W/m after losses is reasonable)
Power Architecture
http://www.asciiflow.com/#4007824742034929919/13747898[YOB-2] +--------------+ +--->| LED Strip 0 | | +--------------+ | | +--------------+ +---------------+ | +->| LED Strip 1 | +--------------+ | +-+ | +--------------+ | | | StrichLux +---+ | Dome | +->| Controller A +---+ +--------------+ | Lighting | | | +-+ +->| LED Strip 2 | | | | +---------------+ | +--------------+ +--------------+ | | ^ | | +--------------+ | | +--->| LED Strip 3 | +----------+---------+ | +--------------+ | | | | | | +--------------+ | +-+ +--->| LED Strip 4 | | | | +--------------+ | | | | | | +--------------+ | | +---------------+ | +->| LED Strip 5 | +---------------+ | | | +-+ | +--------------+ | | | Distribution | | StrichLux +---+ | Battery +=======>| +--->| Controller B +---+ +--------------+ | | | Box | | +-+ +->| LED Strip 6 | +---------------+ | | +---------------+ | +--------------+ | | | | | | +--------------+ | | +--->| LED Strip 7 | | | +--------------+ | +-+ | | | +--------------+ +--+-------+---------+ | +--->| LED Strip 8 | | | | | +--------------+ +---------+ | | | v v | | +--------------+ +--------------+ +--------------+ | +---------------+ | +->| LED Strip 9 | | | | | | | +-+ | +--------------+ | Convienience | | System | | | StrichLux +---+ | Outlets | | Controller | +->| Controller C +---+ +--------------+ | | | | | | +->| LED Strip 10 | +--------------+ +--------------+ +---------------+ +--------------+
Lighting Layout
Random Notes
- Decided on 60m length total (3 StrichLux boxes)
- That's 1920 RGB LEDs and ~600W peak!
- Will need to come up with a lighting layout/design that will fit within this
Dimensions
Main Module (4 of these vertically, 2 of which will be lit) ----------------------------------------------------------- +-----D-----+------E------+ |\ /| | | | | \ / | |-----D-----| | | F / | | H | | \ / | |-----D-----| | | \ / | | | | | / \ | |-----D-----+------E------| | / \ | | | | F \ | A A A / \ A |-----------B-------------+ |/ \| Top Module ---------- | | | | | | | | | | | | | | | | |-------B-----------------| |------------------C------------------| | | | | / \ | | G | |------------------C------------------| | | | | | A============B============A A A | | | |
- A - Module Height (5ft 1in)
- B - Module Width (5ft)
- C - Module Depth (7ft)
- D - Ladder Width (2.5ft)
- E - Beside-Ladder Width (B - D) (2.5ft)
- F - Cross-brace Length (7.37ft)
- G - Top Rail Support Height
- H - Ladder Section Height (3.5ft)
- n - Number of Modules (3)
- x - Number of Main Modules (2)
Idealized Layout
- Vertical Mains: A * 4 * n = 5.083 * 4 * 3 = 61ft (done piecing)
- Beside-Ladder Boxes: (E * 2 + H) * 2 * x = 34ft (done piecing)
- Cross-braces: F * 2 * 2 * x = 7 * 2 * 2 * 2 = 59ft (done piecing)
- Top Rail: B * 2 + C * 2 = 24ft (done piecing)
- Top-Middle Rail: C * 2 = 14ft (done piecing)
- Toe Board: B * 4 = 10ft (done piecing)
- Total: 202ft / 61.5m
Actual Layout
- Vertical Mains: 4.5m each * 4
- Cross brace tubes: 1.125m each * 8
- Toe board: 1.5m each * 2
- Top middle rail: 2.1m each * 2
- Top rail long side: 2.1m each * 2
- Top rail short side: 1.5m each * 2
- Ladder box vertical: 1m each * 4
- Ladder box horizontal: 0.75m * 8
- Total: 60.00m
Universe <-> Controller Mapping
Since physical locations of the controllers changed after all the channels were laid out, the universe numbers don't map linearly to the controller channels anymore.
- Controller A (Base of VM2)
- A-1 - U0
- A-2 - U1
- A-3 - U5
- A-4 - U6
- Controller B (Base of VM3)
- B-1 - U2
- B-2 - U7
- B-3 - U9
- B-4 - U10
- Controller C (Base of VM4)
- C-1 - U3
- C-2 - U4
- C-3 - U8
- C-4 - U11
LED Strip List
ID | Piece | Location | Length | # of LEDs | Reel | Universe | DMX Channels | LightJams IDs |
---|---|---|---|---|---|---|---|---|
S01 | Vertical Main 1 | Vertical Main 1 | 450cm | 144 | C | U0 | 1-432 | BAA-BFN |
S02 | Vertical Main 2 | Vertical Main 2 | 450cm | 144 | D | U1 | 1-432 | CAA-CFN |
S03 | Vertical Main 3 | Vertical Main 3 | 450cm | 144 | E | U2 | 1-432 | DAA-DFN |
S04 | Vertical Main 4 | Vertical Main 4 | 450cm | 144 | F | U3 | 1-432 | EAA-EFN |
S05 | Cross brace tube 1 | MF1/2 B Right | 218.75cm | 70 | G | U4 | 1-210 | FAA-FCR |
S06 | Cross brace tube 2 | MF1/2 A Right | 218.75cm | 70 | G | U5 | 1-210 | GAA-GCR |
S07 | Cross brace tube 3 | MF1/2 A Left | 218.75cm | 70 | H | U6 | 1-210 | HAA-HCR |
S08 | Cross brace tube 4 | MF1/2 B Left | 218.75cm | 70 | H | U6 | 211-420 | HCS-HFJ |
S09 | Cross brace tube 5 | MF3/4 A Right | 218.75cm | 70 | I | U8 | 1-210 | JAA-JCR |
S10 | Cross brace tube 6 | MF3/4 B Right | 218.75cm | 70 | I | U9 | 1-210 | KAA-KCR |
S11 | Cross brace tube 7 | MF3/4 B Left | 218.75cm | 70 | J | U10 | 1-210 | LAA-LCR |
S12 | Cross brace tube 8 | MF3/4 A Left | 218.75cm | 70 | J | U10 | 211-420 | LCS-LFJ |
S13 | Toe board 1 | 1 (Close) | 150cm | 48 | A | U11 | 349-492 | MEM-MGH |
S14 | Toe board 2 | 2 (Far) | 150cm | 48 | A | U11 | 1-144 | MAA-MBV |
S15 | Top middle rail 1 | Left | 212.5cm | 68 | K | U11 | 145-348 | MBW-MEL |
S16 | Top middle rail 2 | Right | 212.5cm | 68 | K | U8 | 307-510 | JDY-JGN |
S17 | Top long rail 1 | Right | 212.5cm | 68 | L | U9 | 307-510 | KDY-KGN |
S18 | Top long rail 2 | Left | 212.5cm | 68 | L | U7 | 145-348 | IBW-IEL |
S19 | Top short rail 1 | TF1 | 150cm | 48 | B | U7 | 1-144 | IAA-IBV |
S20 | Top short rail 2 | TF2 | 150cm | 48 | B | U7 | 349-492 | IEM-IGH |
S21 | Ladder box vertical 1 | MF1 | 100cm | 32 | A | U4 | 283-378 | FDQ-FEV |
S22 | Ladder box vertical 2 | MF2 | 100cm | 32 | A | U5 | 283-378 | GDQ-GEV |
S23 | Ladder box vertical 3 | MF3 | 100cm | 32 | B | U8 | 211-306 | JCS-JDX |
S24 | Ladder box vertical 4 | MF4 | 100cm | 32 | B | U9 | 211-306 | KCS-KDX |
S25 | Ladder box horizontal 1 | MF1 Top | 75cm | 24 | C, D | U4 | 211-282 | FCS-FDP |
S26 | Ladder box horizontal 2 | MF1 Bottom | 75cm | 24 | E, D | U4 | 379-450 | FEW-FFT |
S27 | Ladder box horizontal 3 | MB2 Top | 75cm | 24 | K | U5 | 211-282 | GCS-GDP |
S28 | Ladder box horizontal 4 | MF2 Bottom | 75cm | 24 | L | U5 | 379-450 | GEW-GFT |
S29 | Ladder box horizontal 5 | MF3 Top | 75cm | 24 | G, H | U0 | 433-504 | BFO-BGL |
S30 | Ladder box horizontal 6 | MF3 Bottom | 75cm | 24 | I, H | U1 | 433-504 | CFO-CGL |
S31 | Ladder box horizontal 7 | MF4 Top | 75cm | 24 | J, H | U2 | 433-504 | DFO-DGL |
S32 | Ladder box horizontal 8 | MF4 Bottom | 75cm | 24 | F, H | U3 | 433-504 | EFO-EGL |
Reel Assignment
- Reel A (100% used)
- Toe Board 1: 150cm
- Toe Board 2: 150cm
- Ladder box vertical 1: 100cm
- Ladder box vertical 2: 100cm
- Reel B (100% used)
- Top short rail 1: 150cm
- Top short rail 2: 150cm
- Ladder box vertical 3: 100cm
- Ladder box vertical 4: 100cm
- Reel C (100% used)
- Vertical Main 1: 450cm
- Ladder box horizontal 1a: 50cm (chunk 1)
- Reel D (100% used)
- Vertical Main 2: 450cm
- Ladder box horizontal 1b: 25cm (chunk 2)
- Ladder box horizontal 2b: 25cm (chunk 2)
- Reel E (100% used)
- Vertical Main 3: 450cm
- Ladder box horizontal 2a: 50cm (chunk 1)
- Reel F (100% used)
- Vertical Main 4: 450cm
- Ladder box horizontal 8a: 50cm (chunk 1)
- Reel G (100% used)
- Cross brace tube 1: 218.75cm
- Cross brace tube 2: 218.75cm
- Ladder box horizontal 5a: 62.5cm (chunk 1)
- Reel H (100% used)
- Cross brace tube 3: 218.75cm
- Cross brace tube 4: 218.75cm
- Ladder box horizontal 5b: 12.5cm (chunk 2)
- Ladder box horizontal 6b: 12.5cm (chunk 2)
- Ladder box horizontal 7b: 12.5cm (chunk 2)
- Ladder box horizontal 8b: 25cm (chunk 2)
- Reel I (100% used)
- Cross brace tube 5: 218.75cm
- Cross brace tube 6: 218.75cm
- Ladder box horizontal 6a: 62.5cm (chunk 1)
- Reel J (100% used)
- Cross brace tube 7: 218.75cm
- Cross brace tube 8: 218.75cm
- Ladder box horizontal 7a: 62.5cm (chunk 1)
- Reel K (100% used)
- Top middle rail 1: 212.5cm
- Top middle rail 2: 212.5cm
- Ladder box horizontal 3: 75cm
- Reel L (100% used)
- Top long rail 1: 212.5cm
- Top long rail 2: 212.5cm
- Ladder box horizontal 4: 75cm
Cable Routing
- Overview
- When viewing the tower end-on with the ladder on the left:
- Vertical Main 1 is on the left of the close end
- Vertical Main 2 is on the right of the close end
- Vertical Main 3 is on the left of the far end
- Vertical Main 4 is on the right of the far end
- Main Frame 1 is the lower close frame of the 2 lit ones
- Main Frame 2 is the lower far frame of the 2 lit ones
- Main Frame 3 is the higher close frame of the 2 lit ones
- Main Frame 4 is the higher far frame of the 2 lit ones
- Top Frame 1 is the close top frame
- Top Frame 2 is the far top frame
- Cross Brace A are the tubes running low-to-high from MF1/3 to MF2/4
- Cross Brace B are the tubes running high-to-low from MF1/3 to MF2/4
- Toe Board 1 is the close board
- Toe Board 2 is the far board
- When viewing the tower end-on with the ladder on the left:
- Controller A
- Channel 1
- Feeder (up VM1) -> Vertical Main 1 -> Long Jumper (via Toe Board 1, down VM2) -> MF3 LBH Top
- Channel 2
- Feeder (up VM2) -> Vertical Main 2 -> Long Jumper (down VM2) -> MF3 LBH Bottom
- Channel 3
- Feeder (up VM3) -> Vertical Main 3 -> Long Jumper (via Toe Board 2, down VM4) -> MF4 LBH Top
- Channel 4
- Feeder (up VM4) -> Vertical Main 4 -> Long Jumper (down VM4) -> MF4 LBH Bottom
- Channel 1
- Controller B
- Channel 1
- Feeder (up VM4) -> CB MF1/2 B Right -> MF1 LBH Top -> MF1 LBV -> MF1 LBH Bottom
- Channel 2
- Feeder (up VM2) -> CB MF1/2 A Right -> MF2 LBH Top -> MF2 LBV -> MF2 LBH Bottom
- Channel 3
- Feeder (up VM1) -> CB MF1/2 A Left -> Short Jumper -> CB MF1/2 B Left
- Channel 4
- Feeder (up VM3) -> Short Jumper (via TF2 Top Short Rail) -> TF2 Top Short Rail -> Left Top Long Rail -> TF1 Top Short Rail
- Channel 1
- Controller C
- Channel 1
- Feeder (up VM4) -> CB MF3/4 A Right -> Short Jumper -> MF3 LBV -> Long Jumper (via MF3 LBH Top, VM2) -> Right Top Middle Rail
- Channel 2
- Feeder (up VM2) -> CB MF 3/4 B Right -> Short Jumper -> MF4 LBV -> Long Jumper (via MF4 LBH Top, VM4) -> Right Top Long Rail
- Channel 3
- Feeder (up VM3) -> CB MF3/4 B Left -> Short Jumper -> CB MF 3/4 A Left
- Channel 4
- Feeder (up VM4) -> Toe Board 2 -> Left Top Middle Rail -> Toe Board 1
- Channel 1
Feeders and Jumpers
- Feeders
- Feeder A-1 - 310cm (F01)
- Feeder A-2 - 310cm (F02)
- Feeder A-3 - 310cm (F03)
- Feeder A-4 - 310cm (F04)
- Feeder B-1 - 360cm (F05)
- Feeder B-2 - 360cm (F06)
- Feeder B-3 - 360cm (F07)
- Feeder B-4 - 711cm (F08)
- Feeder C-1 - 576cm (F09)
- Feeder C-2 - 576cm (F10)
- Feeder C-3 - 516cm (F11)
- Feeder C-4 - 687cm (F12)
- Jumpers
- Jumper A-1 - 308cm (J01)
- Jumper A-2 - 262cm (J02)
- Jumper A-3 - 308cm (J03)
- Jumper A-4 - 262cm (J04)
- Jumper B-3 - 92cm (J05)
- Jumper B-4 - 152cm (J06)
- Jumper C-1.1 - 73cm (J07)
- Jumper C-1.2 - 142cm (J08)
- Jumper C-2.1 - 73cm (J09)
- Jumper C-2.2 - 142cm (J10)
- Jumper C-3 - 92cm (J11)
Pinouts
Power+Data Cables
Signal | Wiring Colour | MX150L Pin | RT360 Pin |
---|---|---|---|
GND | White | 1 | A |
+5V | Black | 2 | B |
Data | Red | 3 | 1 |
Clock | Green | 4 | 2 |
Power Only Cables
Signal | Wiring Colour | RT360 Pin |
---|---|---|
Bus A+B Negative | Black | A |
Bus A Positive | Green | B |
N/C | N/C | C |
Bus B Positive | White | D |
StrichLux Enclosures
- Each StrichLux controller with its 4 output modules, 1 input module, and 1 power module will need an enclosure of some kind.
- Pelican case? Could do one larger one with all 3 controllers in it, or 3 smaller ones
- Assuming each StrichLux box has its own enclosure, would need a bunch of connections made through it:
- Power - 2x12V @ 20A each - 4 20A power pins
- Ethernet input - RJ45 - 1 RJ45
- Will use M12 ethernet connectors (either from L-com or wherever else we're getting connectors) rather than RJ45s as they're cheap and IP67
- Not RJ45-compatible, but an M12->RJ45 cable will be brought for troubleshooting, and they're not expensive
- Will use M12 ethernet connectors (either from L-com or wherever else we're getting connectors) rather than RJ45s as they're cheap and IP67
- Strip outputs - SPI+5V - 2 signal pins, 2 10A power pins each x 4
- JAE SRCN2A16-7S / SRCN6A16-7P would be good and extremely rugged, but the cost may be too high
- Not weatherproof, doh!
- Amphenol SINE MotionGrade M23/M40-series connectors look really nice, aren't too badly priced (compared with 5015 connectors anyway) and are weatherproof
- They're really tall though, sticking out would negatively affect durability, so RT360 connectors might be better (but a bit more expensive)
- Pricing is Receptacle, Sockets, Plus, Pins, Grip/Shell (* 4 per box * 3 boxes)
- SINE M23: (6.46 + 0.728*4 + 8.430 + 0.640*4 + 3.61) * 4 = $95.88 * 3 = $287.64
- SINE M40: (8.09 + 1.660*4 + 11.05 + 1.780*4 + 7.83) * 4 = $162.92 * 3 = $488.76
- SINE RT360: (4.85 + 0.351*4 + 12.28 + 0.351*4 + 6.62) * 4 = $106.23 * 3 = $318.69
- JAE SRCN2A16-7S / SRCN6A16-7P would be good and extremely rugged, but the cost may be too high
- Molex MX150L will be used for inter-strip connections
- Reasonably priced
- Tooling is reasonably priced
- Matte sealed
Enclosure Connectors
Function | Description | Part # | Qty Req'd per Enclosure | Status |
---|---|---|---|---|
Ethernet Connector | Female Panel Mount Receptacle | CON-M124PF | 1 | Ordered |
Power Connector | Male Flanged Receptacle | RT00144PNH | 1 | Ordered |
Power Connector | Male Pins | SP12A1T | 4 | Ordered |
Power Connector (mating) | Female Cable Plug | RT06144SNH | 1 | Ordered |
Power Connector (mating) | Female Sockets | SS12A1T | 4 | Obtained |
LED Connector | Female Flanged Receptacle | RT00142SNH | 4 | Ordered |
LED Connector | Female Power Sockets | SS12A1T | 8 | Obtained |
LED Connector | Female Signal Sockets | SS20M1T | 8 | Obtained |
LED Connector (mating) | Male Cable Plug | RT06142PNH | 4 | Ordered |
LED Connector (mating) | Male Power Pins | SP12A1T | 8 | Ordered |
LED Connector (mating) | Male Signal Pins | SP20M1T | 8 | Obtained |
Inter-Strip Connectors
Description | Part # | Qty Req'd | Status |
---|---|---|---|
Female Receptacle | 19418-0019 | 51 | Obtained |
Female Crimp Socket | 19420-0001 | 204 | Obtained |
Male Plug | 19419-0004 | 51 | Obtained |
Male Crimp Pin | 19417-0047 | 204 | Obtained |
Test Setup
- Want to be able to power the whole setup from AC power for configuration/testing/programming
- ATX power supplies provide plenty of +12V which could feed the PWR-DC5 modules
- A modular supply like the OCX ZT-series would be cleanest, could modify the cables with Sabre connectors on the ends
- Need 100W per channel, 200W per board, 600W total @ 12V
- 100W per channel @ 12V means 8.33A
- PCI-E and 8-pin CPU power connectors on ATX PSUs provide 6 amps per pin
- PCI-E connectors have 3 pin pairs each
- 8-pin CPU power connectors have 4 pin pairs each
- Need four pins per board
- Two boards get 8-pin CPU power -> Sabre connectors
- The last board gets a 2xPCI-E power -> Sabre connector
- OCZ ZT-series 750W power supply has all the required connectors
- ATX power supplies provide plenty of +12V which could feed the PWR-DC5 modules
Lighting Programs
Specific Programs
- Program 1 - Moving Rainbow
- Track: ???
- Rainbow pattern moves along the track
- Program 2 - Wandering LEDs
- Track: 4 parallel tracks, each following:
- Counterclockwise along top rail to VM
- Down VM to top MF bottom LBH, loop around LB
- Down VM and repeat the loop at the bottom MF
- Down VM to the very bottom then up the CB
- Not included: middle rails, toe boards, top CBs
- A number of LEDs wander around the track randomly
- Track: 4 parallel tracks, each following:
- Program 3 - Random Flashes (programming complete)
- Brief flashes of random LEDs/groups of LEDs
- Program 4 - Random Fades
- Fading in/out of random groups of LEDs
Program Ideas
From Jammies
- a quick-moving plasma effect scaling upwards, with LEDs at the top glowing more and more brightly white, that makes the tower look like it's "powering up"
LightJams Snippets
- Random stepped values over time: if(randpulse(1, 75, 0.01), gmem(0, rand(0, 100)), grecall(0))
- Bouncing (still needs work at the top): fadein.linear(1.5, fadeout(2.5, pulse(3.5, 1)))
Cost
Item | Status | Cost |
---|---|---|
IO-DMX + IO-BO Rev. 1 PCBs | Obtained | $40.69 |
IO-DMX + IO-BO Parts | Obtained | $18.31 |
IO-SPI Rev. 1 PCBs | Obtained | $49.65 |
CORE + IO-ETH + PWR-DC5 PCBs | Obtained | $454.66 |
CORE + IO-SPI + IO-ETH + PWR-DC5 Parts | Obtained | $184.40 |
Test LED Strip | Obtained | $25.00 |
OCZ ZT 750W Test PSU | Obtained | $107.34 |
60m LPD8806 LED Strip | Obtained | $1320.00 |
Fit-PC 2i | Obtained | $455.00 |
Lightjams License (design PC) | Obtained | $78.59 |
Lightjams License (installation PC) | Obtained | $78.59 |
Ethernet Switch | Obtained | $363.85 |
2 sets of StrichLux IO-CORE + IO-ETH + PWR-DC5 Parts | Obtained | $512.83 |
12 sets of StrichLux IO-SPI Parts | Obtained | $190.39 |
Enclosure A | Obtained | $62.15 |
Enclosures B-D | Future | $186.45 |
Enclosure Connectors (order 1) | Obtained | $563.09 |
Enclosure Connectors (order 2) | Obtained | ~$0.00 |
Inter-Strip Connectors (order 1) | Obtained | $320.55 |
Inter-Strip Connectors (order 2) | Ordered | $30.01 |
250ft 14/4 SJOOW Cable | Ordered | $371.44 |
SSD for Controller | Obtained | $101.69 |
Windows License for Controller | Obtained | $113.00 |
Shipping (outbound) | Done | $455.92 |
Tax/Duty (outbound) | Done | $104.40 |
Shipping (return) | Done | $224.29 |
Tax/Duty (return) | Done | $443.06 |
Total | Ordered | $6668.90 |
Total | Future | $0.00 |
Grand Total | $6668.90 | |
Hours Spent | 577 |